“First concrete was poured for the base slab of unit 3’s nuclear island in March 2021, with that of unit 4 being poured in the December of that year. Changjiang Phase II – units 3 and 4 – represents a total estimated investment of CNY40 billion (USD5.9 billion), according to China Huaneng, which holds a 51% share in the project. Both units are scheduled to be fully operational in early 2027.”
“Changjiang 3 achieved first criticality – a sustained chain reaction – on 10 July this year and was connected to the grid on 1 August.”
“The island province of Hainan is China’s southernmost point. Energy policies published in 2019 by Hainan Province Development and Reform Commission specify that nuclear power will become the primary source of electricity for the island, which has a population of close to 10 million.”
” ‘Upon full completion, the Phase II project is expected to generate 18 billion kilowatt-hours of clean electricity annually, replacing more than 6.32 million metric tons of standard coal and reducing carbon dioxide emissions by about 11.6 million tons every year,’ Liu Bin, general manager of Huaneng Hainan Changjiang Nuclear Power Company Ltd was quoted as saying by China Daily. ‘This will provide a clean, safe, and efficient power supply to anchor the construction of the Hainan Free Trade Port while accelerating the nation’s progress toward its dual-carbon targets’.”
https://world-nuclear-news.org/articles/third-unit-at-changjiang-site-commissioned
See also: Blue economy is the next key phase of China-ASEAN economic integration
“Zhang Jianping, senior research fellow and vice-chairman of the Academic Committee, Chinese Academy of International Trade and Economic Cooperation, Ministry of Commerce, said Hainan and Guangxi both occupy hub positions on the New Western Land-Sea Corridor and expressed hope that the Pinglu Canal’s opening will secure infrastructure, transport and logistics links between the Hainan FTP and ASEAN, deepening the flow of goods, people and services.”