“A seven-phase licensing roadmap for nuclear power projects has been finalized and is ready to be presented to parties interested to invest in nuclear power, the Department of Energy (DOE) said Tuesday.”
“The phases cover business registration and permits; environmental clearances and siting; licensing by the Philippine Atomic Energy Regulatory Authority (PhilAtom) to build or obtain a provisional permit; sector-specific approvals; operational permits; construction oversight; and licensing for operation, testing and commissioning.”
“The framework was crafted during a Feb. 11 meeting attended by over 100 stakeholders, led by Energy Undersecretary Rowena Cristina Guevara, Finance Undersecretary Catherine Fong, and Philippine Nuclear Research Institute Director Carlo Arcilla.”
“Energy Secretary Sharon Garin said the government plans to begin accepting nuclear plant license applications this year.”